A £550,000 scheme to prolong the life of the A59 at Kex Gill is set to begin in preparation for the opening of a new road in 2025.
Major resurfacing scheme to prepare for Kex Gill unveiling
A £550,000 scheme to prolong the life of one of the most important routes in the North of England is set to begin in preparation for the opening of a new road in 2025.
North Yorkshire Council’s highways team will begin a five-week programme of work on the A59 at Kex Gill to the west of Harrogate, next to where the newly-aligned road will start.
The £550,000 resurfacing and landslip scheme between Church Hill and Pace Gate on the A59 is being funded by the extra £6.5 million which North Yorkshire Council was awarded in this year’s Spring Budget.
It was among the top three councils to benefit from the funding.
Resurfacing will take place on a section of the A59 which will remain in use when the new road opens.
Officers will be carrying out essential stabilising works to the slope of the existing road as well as drainage repairs, gully-clearing, refreshing lining, replacing cat’s eyes and maintenance of the ground monitoring equipment.
The five-week scheme will begin on Monday 9th October, and will require a full road closure. Advance warning signs and a signed diversion will be in place.
North Yorkshire Council’s executive member for highways and transport, Cllr Keane Duncan, said:
“Keeping our roads in the best condition for the money that we have available is one of the biggest challenges that we face, so the additional government investment is making a huge difference to this year’s highways budget.
“It is allowing us to complete even more works than expected, including this key section of the A59.
“Kex Gill has a history of landslips, and the route has had to be closed a total of 12 times in the past 22 years. We must stabilise the slope near the existing road to avoid any lengthy closures over the next two years whilst the new road is constructed.
“Although there is never a good time to carry out such works, they need to be completed before the inclement winter weather hits.
“We have also timed the other essential works during the five-week period to avoid further closures and have been liaising with neighbouring authorities to ensure an appropriate diversion route has been set up and agreed.”
The Department for Transport is providing grant funding of £56.1 million for the £68.8 million Kex Gill re-alignment project, with the remaining £12.7 million allocated from North Yorkshire Council’s capital reserves.
A new four-kilometre stretch of road will be created, replacing an existing part of the A59 which has been affected by the landslips.
The re-aligned route will leave the A59 at North Moor Road and re-join the existing road at Blubberhouses. It is due to be completed by autumn 2025.
The road, which runs across a rural stretch of the county on the edge of the Yorkshire Dales National Park, has been identified by the Government as one of the most important strategic routes nationally as it provides a key link running across the country.
Read more local stories from Your Harrogate here.
Council looks to buy new council houses in Ripon
Ripon school and cathedral launch first boarding scholarship
Storm Goretti: Yellow weather warning for snow in Harrogate
Harrogate clinician awarded King's Ambulance Medal in New Year Honours
New right-to-buy policy to be introduced by North Yorkshire Council
80s popstar Sinitta heaps praise on Harrogate after festive trip
Harrogate Town Council confirm precept hike in 2026/27 budget
Harrogate MP slams Government's "disgraceful" bid to dismantle jury trials
Harrogate café listed for sale after just 15 months
RHS Harlow Carr announces record-breaking visitor numbers
The Traitors star urges sign-ups for Harrogate Race for Life
When the weather turns, turn to Your Harrogate
Government urged to help fund rising costs of special needs education in North Yorkshire
Inspectors praise maternity services at Harrogate District Hospital
Taylor Wimpey submits plans for 320 homes off Penny Pot Lane
Popular Harrogate cheese shop to relocate next week
Harrogate MP renews push to scrap disabled bus pass restriction
New Pilates Studio to open in Harrogate next week
Lightwater Valley announces 'exciting new era' under new ownership
Will we get snow in the Harrogate district?


